Topic 1: Volume A
Which product is NOT created in the Managing a Stage Boundary process?
A.
Benefits Review Plan
B.
End Stage Report
C.
Lessons Report
D.
Exception Plan
Benefits Review Plan
If Work Package tolerance is forecast to be exceeded, to whom should the Team Manager
report?
A.
Corporate management
B.
Project Board
C.
Project Assurance
D.
Project Manager
Project Manager
Which statement about risks is FALSE?
A.
A risk that could have a positive impact on a project's objectives is known as an
opportunity
B.
A risk that could have a negative impact on a project's objectives is known as a threat
C.
A risk that a project's product is incomplete is known as an off-specification
D.
A risk is an uncertain event that, should it occur, will have an effect on a project's
objectives
A risk that a project's product is incomplete is known as an off-specification
Which should be funded from a change budget?
A.
The Starting up a Project process
B.
A fallback plan
C.
An agreed change to the scope of a project
D.
A change to a plan, within allocated tolerances, due to poor estimating
An agreed change to the scope of a project
Which is a purpose of the Directing a Project process?
A.
Provide the information required to confirm if it is worthwhile to initiate a project
B.
Enable overall control of a project to be exercised by the Project Board
C.
Establish the level of control required by the Project Board after initiation
D.
Provide sufficient information so that the currentstage can be reviewed and the next
Stage Plan approved
Enable overall control of a project to be exercised by the Project Board
Which statement is true for ALL project stakeholders?
A.
Internal to the corporate organization
B.
May either affect or be affected by the project
C.
Review the Communication Management Strategy
D.
Support the project
May either affect or be affected by the project
Which PRINCE2 principle helps to address a concern that the project team may NOT have
worked on a similar project?
A.
Defined roles and responsibilities
B.
Learn from experience
C.
Manage by exception
D.
Focus on products
Learn from experience
What is the collective name for individuals or groups who may be affected by a project?
A.
Customers
B.
Project Support
C.
Stakeholders
D.
Team members
Stakeholders
Which enables the project's products and all interdependencies to be clearly identified and
documented?
A.
Product breakdown structure
B.
Quality Management Strategy
C.
Product-based planning technique
D.
Quality review technique
Product-based planning technique
Which is a responsibility of a Team Manager?
A.
Producing Highlight Reports for the Project Manager
B.
Reviewing the status of the stage
C.
Setting WorkPackage tolerances
D.
Ensuring delivery of products in the Managing Product Delivery process
Ensuring delivery of products in the Managing Product Delivery process
In what product should the quality criteria for a specialist product be recorded?
A.
Quality Management Strategy
B.
Quality Register
C.
Product Description
D.
Project Product Description
Product Description
Which product describes the roles and responsibilities for achieving the effective
management of anticipated threats and opportunities in a project?
A.
Quality Management Strategy
B.
Risk Management Strategy
C.
Communication Management Strategy
D.
Configuration Management Strategy
Risk Management Strategy