Prince2-Foundation Practice Test Questions

276 Questions


Topic 1: Volume A

Which is a purpose of a Product Description?


A.

Provide the cost tolerance available for individual products


B.

Define reporting frequency


C.

Record the quality checks completed for the End Stage Report


D.

Document the level of quality required of a product





D.
  

Document the level of quality required of a product



Identify the missing words in the following sentence. An objective of the Directing a Project
process is to [?] throughout a project's life,


A.

document how risks will bemanaged


B.

identify who will be responsible for quality


C.

provide management direction and control


D.

define the benefits to be realized





C.
  

provide management direction and control



Which is a purpose of the Plans theme?


A.

Identify, assess and control any potential changes to the baseline


B.

Establish the project's structure of accountability


C.

Assess and control uncertainty


D.

Understand whether the targets are achievable





D.
  

Understand whether the targets are achievable



Who represents the three project interests on a project?


A.

Project Manager


B.

Project Support


C.

External project stakeholders


D.

Project Board





D.
  

Project Board



When are tolerances for a Work Package agreed?


A.

When acceptinga Work Package


B.

As work on each product within the Work Package begins


C.

Once ail products have been developed and approved


D.

 When the Stage Plan is authorized by the Project Board





A.
  

When acceptinga Work Package



How should the Team Manager report that tolerances are forecast to be exceeded?


A.

Create an Exception Report


B.

Create a Highlight Report


C.

Raise an issue


D.

Grant a concession





C.
  

Raise an issue



What process aims to ensure accurate progress information is provided to the Project
Manager?


A.

Starting up a Project


B.

Managing a Stage Boundary


C.

Managing Product Delivery


D.

Directing a Project





C.
  

Managing Product Delivery



Which is a purpose of the Risk theme?


A.

Establish a procedure to ensure every change is agreed by the relevant authority before
it takes place


B.

Establish a cost-effective procedure to identify, assess and control uncertainty


C.

Establish mechanisms to control any unacceptable deviations from plan


D.

Establish mechanisms to manage risks at the corporate or programme level of an
organization





B.
  

Establish a cost-effective procedure to identify, assess and control uncertainty



Which is a difference between management and technical stages?


A.

Management stages require planning and technical stages do not


B.

Technical stages can overlap and management stages cannot


C.

Management stages deliver products and technical stages do not


D.

Technical stages require resources and management stages do not





B.
  

Technical stages can overlap and management stages cannot



Which process provides the Project Board with the information it requires in order to
commit
resources to the project?


A.

Managing Product Delivery


B.

Initiating a Project


C.

Controlling a Stage


D.

Directinga Project





B.
  

Initiating a Project



During the Managing a Stage Boundary process what product is updated with estimated
costs and time for the stage that is about to begin?


A.

End Stage Report


B.

Team Plan


C.

Work Package


D.

Project Plan





D.
  

Project Plan



Identify the missing words in the following sentence, The six aspects of project
performance to be managed are [?] costs, timescales and scope,


A.

benefits, progress, risk,


B.

benefits, quality, risk,


C.

change, quality, progress,


D.

benefits, customers, quality,





B.
  

benefits, quality, risk,