Topic 1: Volume A
Which is a purpose of quality planning?
A.
Define the structure of the project management team
B.
Detail the acceptance criteria, in order for the Project Board to agree the level of quality
expected of the project's product
C.
Document approval records for those project products that have met their quality criteria
D.
Produce the Project Plan with resource and schedule information
Detail the acceptance criteria, in order for the Project Board to agree the level of quality
expected of the project's product
Upon what environment is PRINCE2 based?
A.
Operational
B.
Configuration
C.
Programme
D.
Customer/supplier
Customer/supplier
Which product identifies the management stages and timescales of a project?
A.
Project Brief
B.
Project Product Description
C.
Project Plan
D.
Initiation Stage Plan
Project Plan
Which of the following is the Business Case used for during the Managing a Stage
Boundary process?
A.
Enable the Project Board to decide whether or not to authorize the project
B.
Justify the continuing viability of the project
C.
Enable the Project Board to decide whether or not to authorize project closure
D.
Justify the initiation of a project
Justify the continuing viability of the project
Which of the following is NOT part of quality planning?
A.
Define quality responsibilities
B.
Gain acceptance of the project product
C.
Agree acceptance criteria
D.
Set quality tolerances
Gain acceptance of the project product
Which of the following is NOT an event-driven control?
A.
Project mandate
B.
Checkpoint Report
C.
Exception Report
D.
End of a stage
Checkpoint Report
Identify the missing words in the following sentence. An objective of the Closing a Project
process is to ensure that provision has been made to address [?] through follow-on action
recommendations.
A.
the measurement of benefits NOT yet realized
B.
the handover of products
C.
open issues and risks
D.
the release of resources
open issues and risks
Which is a purpose of the Controlling a Stage process?
A.
Produce a Team Plan for the work to be assigned to a Team Manager
B.
Select and implement actions that will resolve deviations from a plan within tolerance
C.
Obtain approvals for products delivered in aWork Package
D.
Update a Project Plan to incorporate the actuals from a Stage Plan
Select and implement actions that will resolve deviations from a plan within tolerance
Who should act as the communication channel between a project and corporate or
programme
management?
A.
Project Board
B.
Project Assurance
C.
Project Manager
D.
Project Support
Project Board
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier
environment?
A.
Specify the desired result
B.
Provide the resources and skills to deliver the desired result
C.
Pay for the project
D.
Specify the benefits of the project
Provide the resources and skills to deliver the desired result
If the Project Board instructs the Project Manager to implement a request for change, which
document would contain details of that change?
A.
Checkpoint Report
B.
Highlight Report
C.
Issue Report
D.
Product Status Account
Issue Report
Which is a responsibility of the managing level within the project management team?
A.
Set project tolerances
B.
Approve stage completion
C.
Ensure that the products areproduced within the constraints agreed with the Project
Board
D.
Appoint the project management team
Ensure that the products areproduced within the constraints agreed with the Project
Board