Prince2-Foundation Practice Test Questions

276 Questions


Topic 1: Volume A

Which is NOT a type of issue?


A.

A problem/concern


B.

A constraint


C.

An off-specification


D.

A request for change





B.
  

A constraint



Which is a responsibility of a risk owner?


A.

Identify risks to the project that might occur in their department


B.

Own and authorize theuse of the risk budget to fund risk responses


C.

Manage, monitor and control all aspects of an assigned risk


D.

Determine project risk appetite





C.
  

Manage, monitor and control all aspects of an assigned risk



Which product summarizes progress and is used to decide whether to amend the project
scope or stop the project?


A.

Checkpoint Report


B.

End Stage Report


C.

End Project Report


D.

Product Status Account





B.
  

End Stage Report



Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels
of [?] to reflect the needs of the different levels of management involved in a project,


A.

Management strategies


B.

Plan


C.

Stakeholder interests


D.

Time-driven controls





B.
  

Plan



Which is an objective of the quality review technique?


A.

To baseline a product


B.

To provide a common understanding of what products a project will create


C.

To define the quality methods required within a project


D.

To determine the quality responsibilities of a project team





A.
  

To baseline a product



In what process is the authorization to deliver the project's products given?


A.

Starting up a Project


B.

Initiating a Project


C.

Managing a Stage Boundary


D.

Directing a Project





D.
  

Directing a Project



Which of the following statements about stakeholders are true?
1. Someone who thinks they will be affected by a project is a stakeholder on that project
2. Stakeholders may be internal or external to the corporate organization


A.

Only 1 is true


B.

Only 2 is true


C.

Both 1 and 2 are true


D.

Neither 1 or 2 are true





C.
  

Both 1 and 2 are true



Which may be funded from a risk budget?


A.

Corrections due to off-specifications


B.

Impact analysis of requests for change


C.

Implementation of a fallback plan


D.

Preparation of the Risk Management Strategy





C.
  

Implementation of a fallback plan



Which describes the 'Implement' step within the recommended risk management
procedure?


A.

Project Support will allocate the risk budget to fund the selected risk responses


B.

The risk owner will decide the best response to control the risk


C.

The risk owner and the risk actionee will carry out activities to control and deal with the
risk


D.

The Project Manager will formulate the RiskManagement Strategy





C.
  

The risk owner and the risk actionee will carry out activities to control and deal with the
risk



Which is a purpose of the Managing Product Delivery process?


A.

Enable the Senior Supplier to be provided with sufficient information by the Project
Manager so that they can review the success of the current Work Package


B.

Provide a controlled link between the Project Manager and the Team Manager(s)


C.

Enable the Project Board to requestupdates to the current Team Plan


D.

Establish solid foundations for the project





B.
  

Provide a controlled link between the Project Manager and the Team Manager(s)



Which is an objective of the Managing Product Delivery process?


A.

Sign-off completed Work Packages


B.

Ensure the Business Case is kept under review


C.

Report progress to the Project Board


D.

Ensure that work on products is authorized and agreed with the team





D.
  

Ensure that work on products is authorized and agreed with the team



What is defined as a temporary organization that is created for the purpose of delivering
one or more business products?


A.

Corporate or programme management


B.

A project


C.

A product breakdown structure


D.

A user group





B.
  

A project




Page 3 out of 23 Pages
Previous