Topic 4: Quality Theme
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the service level agreement (SLA) with
the selected service provider?
A.
The SLA must extend for the full duration of the service contract.
B.
Any changes to the SLA must be managed through formal change control.
C.
External consultants are to assist in the creation of the SLA.
D.
The selected service provider should be located locally.
The SLA must extend for the full duration of the service contract.
Which of the following statements are True:
1. Quality management is the complete set of quality standards, procedures and
responsibilities for a site or organization.
2. Quality planning is about defining products required of the project with their respective
quality criteria, methods and responsibilities.
3. Quality control focuses on the operational techniques and activities used to carry out
quality inspections
4. Quality assurance ensures that quality methods are being correctly followed.
A.
1, 2 & 3
B.
1, 3 & 4
C.
1, 2 & 4
D.
2, 3 & 4
1, 2 & 3
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Which statement applies to the Records section?
A.
Delete entry 6 because this information should be included in Stage or Team Plans.
B.
Move entry 6 to the Reporting section because the information should be used to report
on quality activities.
C.
Delete entry 7 because this should be included in the Configuration Management Strategy.
D.
Delete entry 8 because the results of quality reviews are recorded in the Quality
Register
Delete entry 7 because this should be included in the Configuration Management Strategy.
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Which is a correctly defined acceptance criterion for the running cost of the outsourced
service?
A.
Must be kept to a minimum.
B.
Must be kept to a level acceptable to the Ministry of Food Hygiene.
C.
Subject to market conditions.
D.
The annual increase to be less than half the rate of inflation
The annual increase to be less than half the rate of inflation
Extract from the Project Product Description (with errors)
Which 2 statements apply to the Customer's quality expectations section?
A.
Delete entry 16 because this should be shown on the Product Description for the
photos.
B.
Delete entry 17 because this is beyond the scope of this project.
C.
Delete entry 18 because standards should NOT be shown here.
D.
Delete entry 19 because this should appear in the Product Description for the calendar
and not the Project Product Description.
E.
Delete entry 20 because this is an expected benefit and should be recorded in the
Business Case.
Delete entry 17 because this is beyond the scope of this project.
Delete entry 20 because this is an expected benefit and should be recorded in the
Business Case.
Additional Information
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Which statement applies to the Quality standards section?
A.
Delete entry 4 because external suppliers are responsible for applying any relevant standards to their work.
B.
Delete entry 5 because the lack of a change management procedure makes the MFH
document standards unsuitable.
C.
Add 'All contracts must conform to current employment laws".
D.
Add 'PRINCE2 change control procedures will be used to manage any changes to
baselined products'.
Add 'All contracts must conform to current employment laws".
In the PRINCE2 Quality review technique, who would most likely carry out the role of
administrator:
A.
Project manager
B.
Project support
C.
Team Manager
D.
Project Assurance
Project support
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Which statement applies to the Introduction section?
A.
Delete entry 1 because the project approach is defined in the Project Brief.
B.
Delete entry 2 because this is the Project Manager's responsibility.
C.
Delete entry 3 because it is the Project Manager's responsibility to implement the
Quality Management Strategy.
D.
Move entry 3 to the Roles and responsibilities section because this is a quality
responsibility.
Move entry 3 to the Roles and responsibilities section because this is a quality
responsibility.
Extract from the Project Product Description (with errors)
Which 2 statements apply to the Derivation section?
A.
Move entry 9 to Composition because this is within the scope of the project.
B.
Delete entry 10 because this is NOT a source product for this project.
C.
Delete entry 11 as this is already correctly shown under Development Skills required.
D.
Move entry 12 to Composition, because this is within the scope of this project.
E.
Add 'Professional photographer'.
Delete entry 11 as this is already correctly shown under Development Skills required.
Move entry 12 to Composition, because this is within the scope of this project.
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
The service level agreement looks like any other MFH document.
A.
Obtain agreement from the Director of Facilities Division to redesign the service level
agreement within the remaining +2 days tolerance.
B.
Raise an issue (off-specification).
C.
Accept this error as a concession.
D.
No action required.
No action required.
Additional Information
Product Description
Quality notes from the Daily Log
The Director of Information Technology Division (DIT) has been asked to ensure that any
changes to the outsourced staff employment contracts adhere to employment law. The DIT
will review future job descriptions of the transferred staff before the final contract is signed
with the selected service provider.
The service level agreement between MFH and the selected service provider will specify
the type and quality of service required. The selected service provider must follow the
industry standards for providing outsourced services.
MFH has a quality management system which contains a document control procedure for
all its documentation, however this does not include change management.
All project documents will be subject to a quality review. Nominated products will require a
formal approval record signed-off by the quality review chair.
Extract from the draft Quality Management Strategy (may contain errors)
Introduction
1. This document defines the approach to be taken to achieve the required quality levels
during the project.
2. The Project Board will have overall responsibility for the Quality Management Strategy.
3. Project Assurance will provide assurance on the implementation of the Quality
Management Strategy.
Quality management procedure - Quality standards
4. The selected service provider will operate to industry standards for providing outsourced
services.
5. MFH document standards will be used.
Records
6. A Quality Register will be maintained to record the planned quality events and the actual
results from the quality activities.
7. Configuration Item Records will be maintained for each product to describe its status,
version and variant.
8. Approval records for products that require them will be stored in the quality database.
Roles and responsibilities
9. The DIT will check that the employment contracts for outsourced staff adhere to
employment law.
10. Team Managers will provide details of quality checks that have been carried out.
11. Team Managers will ensure that the Quality Register is updated with the names of
team members who are involved in the review process.
12. The Senior User will review the Product Descriptions of the products to be produced by
the selected service provider to ensure that they can be achieved.
Which statement applies to the Roles and responsibilities section?
A.
Delete entry 9 because this should only be recorded in the Product Description.
B.
Delete entry 10 because this is the responsibility of the quality review chair.
C.
Delete entry 11 because only the Project Manager can update the Quality Register.
D.
Amend entry 12 because this is the responsibility of supplier assurance
Amend entry 12 because this is the responsibility of supplier assurance
Extract from the Project Product Description (with errors)