PMP Practice Test Questions

377 Questions


Topic 1: Exam Pool A

A new project manager learns the work assigned to the team has already been decomposed to its lowest level The project manager reviews the work and feels some additional useful information is missing

What should the project manager review?


A.

The project charter and scope statement


B.

The requirements traceability matrix


C.

The business requirement documents (BRD)


D.

The WBS dictionary





A project manager is leading an in-house company project in its very early stages This current project is similar to another project that ended a year ago

What should the project manager do to analyze the involved stakeholders?


A.

Lower the priority of stakeholder engagement as the stakeholders already have knowledge of this kind of project


B.

Use lessons learned from the previous project as a guide for the current project's stakeholder register


C.

Refer to the stakeholder register from the previous project as it was similar to the current project


D.

Document in the risk register that the current project may have different stakeholders than the previous project





A key project stakeholder showed interest in the beginning of a complex agile project but has become less involved as the sprint has progressed due to additional responsibilities A few sprints later, the key stakeholder rejected a feature deliverable The team is reworking the rejected deliverable for the next sprint

What should the project manager have done to avoid this situation?


A.

Involved the key stakeholders in the decision-making process


B.

Customized stakeholder communications based on the stakeholders’ needs


C.

Analyzed the changes in stakeholder attributes


D.

Documented the project vision and objectives





The steering committee has asked a project manager experienced in agile to provide an indication of the time remaining on a medium-sized project What tools can be used to provide this information?


A.

A release burndown chart


B.

Analysis of the business requirements document


C.

Story points for the remaining user stories


D.

Surrogate measurements





During the course of the project several obstacles are identified that are preventing the project from moving forward. What should the project manager do to remove the obstacles?


A.

Have the project team work on other activities


B.

Implement plans to remove the obstacles


C.

Escalate to the project steering committee


D.

Prioritize the obstacles for resolution





The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope.
What should the project manager do?


A.

Move to a Kanban strategy so that work can be reallocated more easily


B.

Decrease the sprint cycle to the average repriontization request by calculating it in days


C.

Set up a meeting with the project team and ask for their opinion on what to do


D.

Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle





The project charter was just approved and the project sponsor has given permission to proceed with the project The program manager has confirmed that one of the requested key resources is also needed on another project at the same time This will affect project delivery

What should the project manager do?


A.

Pay overtime to key resource to get the work done outside of working hours


B.

Have a meeting with project manager of the other project to find a resource optimization solution that works for both projects


C.

Speak with the client to see if the project delivery deadline can be delayed due to resource availability


D.

Talk to the program manager and about prioritizing this project over other projects so the key resources are available





The city has decided to build a new tram station The project will include various approaches The construction and infrastructure work will be accomplished using a predictive life cycle while software will be developed using an iterative life cycle Some neighbors are resisting the project have been asking the mayor to stop the project, and are threatening legal action

What two actions should the project manager take'? (Choose two)


A.

Discuss with the construction team alternatives on moving the new train station to another location.


B.

Publish information on the city’s website about the benefits that the new tram station will bring.


C.

Have a meeting with the mayor and explain the importance of the new train station to the city.


D.

Conduct regular meetings with the neighbors to get their buy-in for the project.


E.

Register this situation as a risk and develop a mitigation plan.





A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead The requested workaround will introduce delays and require additional budget

What should the project manager do?


A.

Request to use the management reserve to keep the schedule


B.

Mitigate risks associated with the workaround to avoid project delays


C.

Proceed with the approved risk response plan.


D.

Discuss the options with the client as part of the change control process





During the implementation phase of a project, a new regulation affects the project, and a critical status meeting discussing the scope changes is required. The project manager discovers that a key stakeholder cannot attend the scheduled meeting

What should the project manager do?


A.

Call for a change control board (CCB) meeting, and inform the stakeholder about the outcome


B.

Update the communications management plan and implement the change


C.

Meet with the project sponsor to discuss how to address the situation.


D.

Meet with the stakeholder prior to the meeting to obtain their opinion





The project manager is reviewing the program risks and issues with key stakeholders One of the stakeholders wants to understand when the risk may potentially become an issue. What artifact should the project manager share with the stakeholder?


A.

Issue log


B.

Project management plan


C.

Risk management plan


D.

Risk register





A project manager is managing a hybrid project After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently.

How should the project manager respond'?


A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced attendance


B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework


C.

Record the issue in the issue log and escalate the conflict to the project sponsor for assistance


D.

Explain to the stakeholder that the stakeholder engagement plan requires their attendance at all reviews






Page 8 out of 32 Pages
Previous