PMP Practice Test Questions

377 Questions


Topic 1: Exam Pool A

In an advanced stage of a project a stakeholder who is not receiving the project status report communicates this to the project manager After checking, the project manager determines that the person is registered as a stakeholder but was not included in the communications management plan.

What should the project manager do next1?


A.

Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder


B.

Inform the project sponsor that there are stakeholders who are not included in the communications management plan


C.

Inform the stakeholder that the project team cannot provide information to anyone who is not registered in the project's communications management plan


D.

Ask the stakeholder to get the project status report from another stakeholder listed in the communications management plan.





A.
  

Update the communications management plan to include the missed stakeholder, and send the current project status documentation to this stakeholder



The communications management plan is a subsidiary plan of the project management plan that describes how project communications will be planned, executed, and monitored. It should include the stakeholder communication requirements, the information to be communicated, the communication methods and technologies, the frequency and timing of communication, the roles and responsibilities of communicators, and the escalation process for resolving communication issues. If a stakeholder is not receiving the project status report, it means that the communications management plan is not aligned with the stakeholder communication requirements, and it needs to be updated. The project manager should also send the current project status documentation to the missed stakeholder to ensure that they are informed and engaged in the project. This is the best option among the four choices, as it follows the best practices of project communication management and stakeholder management. 

References: (Professional in Business Analysis Reference Materials source and documents)

A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Seventh Edition, Chapter 8: Project Communications Management, Section 8.1.3.1: Communications Management Plan

Business Analysis for Practitioners: A Practice Guide, Chapter 4: Planning Business Analysis Work, Section 4.3.2: Communication Plan

Practice Standard for Project Stakeholder Management, Chapter 3: Plan Stakeholder Engagement, Section 3.3.2: Communication Requirements Analysis

A project manager presented the project schedule to the mam stakeholders They have requested that the project be completed two months earlier than the scheduled date

What should the project manager do?


A.

Hold a stakeholder meeting to align timelines and scope expectations.


B.

Crash the schedule to shorten the timeline while keeping the scope unchanged


C.

Update the cost management plan to allocate more resources to the project to finish the scope earlier.


D.

Reduce the scope of the project by removing activities and shortening the timeline





A.
  

Hold a stakeholder meeting to align timelines and scope expectations.



The project manager should hold a stakeholder meeting to align timelines and scope expectations. This is because the project manager needs to manage the stakeholder’s expectations and ensure that they understand the implications of their request. The project manager should explain the current project schedule, the assumptions and constraints that were considered, and the risks and opportunities that are involved. The project manager should also discuss the possible alternatives to meet the stakeholder’s request, such as crashing, fast-tracking, or scope reduction, and their pros and cons. The project manager should seek the stakeholder’s input and feedback, and try to reach a mutually agreeable solution that satisfies the project objectives and the stakeholder’s needs. The project manager should also update the project documents, such as the project management plan, the schedule baseline, and the scope baseline, to reflect the agreed changes, and communicate them to the relevant stakeholders.

The other options are not correct because they do not address the issue of stakeholder alignment and communication, which is essential for project success. Crashing the schedule to shorten the timeline while keeping the scope unchanged might be a possible option, but it would increase the project cost and risk, and might not be acceptable to the stakeholder. Updating the cost management plan to allocate more resources to the project to finish the scope earlier might be another option, but it would also increase the project cost and complexity, and might not be feasible or effective. Reducing the scope of the project by removing activities and shortening the timeline might be another option, but it would compromise the project value and quality, and might not meet the stakeholder’s requirements. References: PMBOK Guide, 6th edition, section 6.6, page 215, PMP Exam Prep, 10th edition, page 180

A team member shares with their functional manager some negative details about the performance of another team member that was discussed during the retrospective. The project manager finds out about this discussion

What two actions should the project manager take? (Choose two)


A.

Contact the team member's functional manager and invite them to the next retrospective


B.

Meet with the entire team to review the ground rules about safe environments


C.

Meet with the product owner to talk about the situation.


D.

Contact the team member to explain what information can be shared outside the team.


E.

Meet with the sponsor to review the situation.





B.
  

Meet with the entire team to review the ground rules about safe environments



D.
  

Contact the team member to explain what information can be shared outside the team.



The project manager should meet with the entire team to review the ground rules about safe environments, as this is an important aspect of creating a high-performing team and fostering trust and collaboration among team members1. The project manager should also contact the team member who shared the negative details to explain what information can be shared outside the team and what information should be kept confidential, as this is part of managing the team’s communication and ensuring ethical behavior2. Contacting the team member’s functional manager and inviting them to the next retrospective (option A) may not be appropriate, as it could violate the privacy of the other team member and create more conflict. Meeting with the product owner to talk about the situation (option C) may not be relevant, as the product owner is not directly involved in the issue and may not have the authority or responsibility to resolve it. Meeting with the sponsor to review the situation (option E) may not be necessary, as the sponsor is not directly involved in the issue and may not have the interest or availability to address it.

References:
1: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, p. 336.
2: A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, p. 379.

After a couple of iterations the project manager decides to present the product to a key stakeholder The stakeholder's feedback is that the team missed the mark on many features.

What should the project manager do to avoid this in the future?


A.

Set up requirements-gathering sessions with all key stakeholders to evaluate the scope once again and reprioritize the backlog based on the sessions.


B.

Schedule adequate sprint demos to gather early feedback from the stakeholders and adapt the plan accordingly


C.

Incorporate design thinking practices into the project life cycle to better understand the product's personas and be more effective to match their needs.


D.

Evaluate the team's skills to look for someone with experience in product design and assign that person the task of rebuilding the product interface





C.
  

Incorporate design thinking practices into the project life cycle to better understand the product's personas and be more effective to match their needs.



Design thinking is a human-centered approach to problem-solving that involves empathy, ideation, prototyping, and testing. It helps project managers and teams to understand the needs, preferences, and pain points of the end users and stakeholders, and to create solutions that are desirable, feasible, and viable. By incorporating design thinking practices into the project life cycle, the project manager can avoid missing the mark on many features and deliver a product that meets or exceeds the stakeholder’s expectations. Some of the design thinking practices that can be applied in the project life cycle are:

Stakeholder mapping: This is a technique to identify and analyze the key stakeholders of the project, their roles, interests, expectations, and influence. It helps to align the project objectives with the stakeholder needs and to plan the communication and engagement strategies. Stakeholder mapping can be done at the initiation stage of the project and updated throughout the project as needed.

Persona creation: This is a technique to create fictional characters that represent the typical end users of the product. Personas help to empathize with the users and to design the product features and functions that suit their needs, goals, and behaviors. Persona creation can be done at the planning stage of the project and validated with real users during the execution stage.

User journey mapping: This is a technique to visualize the steps and interactions that the users go through when using the product. User journey mapping helps to identify the pain points, opportunities, and emotions of the users and to design the product features and functions that enhance their experience. User journey mapping can be done at the planning stage of the project and refined with user feedback during the execution stage.

Prototyping and testing: This is a technique to create and test low-fidelity or high-fidelity versions of the product with the users and stakeholders. Prototyping and testing help to validate the assumptions, gather feedback, and improve the product features and functions. Prototyping and testing can be done iteratively at the execution stage of the project and finalized at the closing stage. 

References:
1: Stakeholder analysis 101: a project manager’s guide - Office Timeline 2: 4 Reasons Project Stakeholder Feedback is Important
3: How to Gather and Control Stakeholder Feedback and Reaction
4: Overcoming the Challenges of Collecting Stakeholder Feedback for Project Management
5: Design Thinking for Project Managers - PMI
6: Design Thinking for Project Management - ProjectManager

A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client How should the project manager proceed?


A.

Update the quality management plan for the overall project


B.

Ask the client to verify and accept the tasks that have been completed


C.

Close out the project tasks that have been completed


D.

Update the communications management plan for the overall project





B.
  

Ask the client to verify and accept the tasks that have been completed



According to the PMBOK Guide, 6th edition, section 4.7, one of the main outputs of the close project or phase process is the final product, service, or result transition. This involves transferring the ownership and responsibility of the project deliverables to the customer or sponsor, and obtaining their formal acceptance and sign-off. The project manager should ensure that the project scope and quality criteria are met, and that the deliverables are aligned with the project objectives and stakeholder expectations. The other options are not appropriate for the end of the project, as they are either part of the planning or monitoring and controlling processes, and do not involve the client’s verification and acceptance. References: PMBOK Guide, 6th edition, section 4.7; PMP Practice Exam, question 86.

A project has a very tight delivery schedule. The project is approaching the delivery date, and the project sponsor often sends the project manager alerts to avoid any schedule slippage . The project team has performed at an acceptable level until new, but the project manager wants to ensure that team’s performance level is performance is maintained until the end.

What action should the project manager take to motivate the project team's performance?


A.

Award certificates of appreciation to encourage the team


B.

Inform the team about the delivery pressure from the project sponsor


C.

Send a formal notice to team members instructing them to maintain performance


D.

Hire a few temporary team members to help with the additional work.





A.
  

Award certificates of appreciation to encourage the team



According to the PBA Guide, one of the techniques for managing stakeholder engagement is recognition and rewards, which can be used to motivate and appreciate the team members for their contributions and achievements1. The PMP Exam Content Outline also lists recognition and rewards as one of the tools and techniques for leading a team2. Awarding certificates of appreciation is an example of recognition and rewards that can boost the team’s morale and performance. Informing the team about the delivery pressure from the project sponsor may increase their stress and anxiety, which can negatively affect their performance. Sending a formal notice to team members instructing them to maintain performance may be perceived as a threat or a punishment, which can also demotivate the team. Hiring a few temporary team members to help with the additional work may introduce new risks and challenges, such as communication issues, learning curves, and integration problems, which can delay the project further.

References:

1: PBA Guide, Chapter 6, Section 6.4.3.5 Recognition and Rewards

2: PMP Exam Content Outline, Domain II: People, Task 8: Lead a team

The sponsor is supportive in leveraging agile approaches The project manager is contemplating how to roll out the agile approach and gam buy-in from both project team members and stakeholders

What should the project manager do first?


A.

Determine which agile software tools will be required to support agile delivery within the organization


B.

Select a current predictive project define the approach, and provide agile training to execute the remainder of the project


C.

Start with a pilot project of appropriate complexity and provide agile training to those who are impacted


D.

Determine how to transform the organization using agile techniques, including organizational training and communications





C.
  

Start with a pilot project of appropriate complexity and provide agile training to those who are impacted



According to the PMBOK Guide, 7th edition, one of the best practices for introducing agile approaches in an organization is to start with a pilot project that has a clear scope, a committed sponsor, and a willing team.

This way, the project manager can demonstrate the benefits of agile, gain feedback, and learn from the experience. The project manager should also provide agile training to the team members and stakeholders who are involved in the pilot project, to ensure they understand the agile principles, values, and practices. References: PMBOK Guide, 7th edition, page 23; Agile Practices and the PMP Certification

During the implementation stage of a project. a newly appointed team leader approaches the project manager to verify the team's tasks and schedule. The work did not go as planned due to the team leader's lack of management experience. This could cause delays for the project.

What should the project manager do?


A.

Ask the human resources director to appoint a senior team leader


B.

Inform the project sponsor about the possible delay


C.

Directly manage the project team to avoid project delays


D.

Provide mentoring to the newly appointed team leader





D.
  

Provide mentoring to the newly appointed team leader



The best option for the project manager in this situation is to provide mentoring to the newly appointed team leader. Mentoring is a process of using experienced members of the organization to provide personal support and guidance to less experienced members of the staff. Mentoring can help the team leader to develop the necessary skills and competencies to manage the team effectively, to overcome challenges, and to achieve the project goals. Mentoring can also foster a positive and collaborative work environment, where the team leader and the team members can learn from each other and share feedback. The project manager can use various techniques and tools to mentor the team leader, such as setting clear expectations, providing regular coaching, giving constructive feedback, sharing best practices, facilitating problem solving, and recognizing achievements. The other options are not as effective as option D. Option A is not feasible, as it may not be possible to find a senior team leader who is available and willing to take over the project. Option B is not proactive, as it only reports the problem, but does not offer any solution. Option C is not empowering, as it undermines the team leader’s authority and responsibility, and may create resentment and demotivation among the team members.

References: (Professional in Business Analysis Reference Materials source and documents)
PMBOK® Guide – Sixth Edition, Chapter 9: Project Resource Management, Section 9.4.2.3: Interpersonal and Team Skills
Mentoring - Key Competency for Program and Project Professionals
How to Improve Your Project Leadership with Coaching and Mentoring?

A project manager is working on a software development project. A team member complains that since the project tasks are very simple, there is no reason to perform quality control The project manager understands that removing the quality management plan from the project will also help to save money, which is important to the customer

What should the project manager do?


A.

Register starting the project without a quality management plan as a risk, and allocate the budget savings to the management reserve


B.

Develop the quality management plan, as quality is as equally important as cost and schedule management.


C.

Get confirmation from management that the team member has enough experience to build software without quality control


D.

Ask the customer to order an external quality audit after accepting the project deliverable, and decrease the budget of the project





B.
  

Develop the quality management plan, as quality is as equally important as cost and schedule management.



A quality management plan is a document that describes how the project team will ensure that the project deliverables meet the quality standards and expectations of the customer and other stakeholders1. Quality is not only about the final product, but also about the processes and activities that produce it2. A quality management plan defines the quality methodology, standards, criteria, activities, tools, resources, reporting, and corrective actions that will be applied throughout the project life cycle to achieve quality objectives3. A quality management plan is important because it helps the project manager and the project team to:

Align the project scope with the customer requirements and needs.
Prevent or minimize defects, errors, and rework.
Enhance customer satisfaction and loyalty.
Improve team performance and collaboration.
Reduce project risks and costs.
Increase project value and benefits Therefore, the project manager should develop the quality management plan, as quality is as equally important as cost and schedule management. Quality is one of the key constraints of the project management triangle, along with scope, time, and cost4. Balancing these constraints is essential for delivering a successful project that meets the expectations of the customer and other stakeholders. Ignoring or compromising quality can have negative impacts on the project outcome, such as poor functionality, usability, reliability, or security of the software product, or low customer satisfaction, trust, or retention. The project manager should also communicate the importance of quality to the team member who complains about quality control, and explain how quality control activities, such as testing, inspection, or review, can help them identify and correct any issues or defects in their work, and ensure that they deliver a high-quality product that meets the customer’s needs and expectations.

References:
The Quality Management Plan in Project Management | ProjectManager.com
What is Quality Management? - Definition from WhatIs.com
What is a Quality Management Plan (QMP) - AcqNotes
Project Management Triangle - Time, Cost and Quality - Iron Triangle
[Why Quality Matters in Software Development - DZone Agile]

During the design phase of a project the project manager notices that the schedule performance index (SPI) is 1 8 and the cost performance index (CPI) is 0 1 In a weekly meeting with top management, the project manager reports concerns about these indicators However the most concerned person was the project sponsor who said that if the trend continues, they will be forced to prematurely close the project

What should the project manager do?


A.

Monitor the project sponsor but understand that it is normal to spend more money in the design phase of a project.


B.

Stop crashing the schedule


C.

Manage the project sponsor closely and revise the project's resource management plan to improve indicators


D.

Use a resource-levelling technique





C.
  

Manage the project sponsor closely and revise the project's resource management plan to improve indicators



According to the PMBOK Guide, the schedule performance index (SPI) and the cost performance index (CPI) are two key indicators of the project performance measurement1. The SPI measures how efficiently the project team is using the time allocated for the project, while the CPI measures how efficiently the project team is using the resources allocated for the project1. An SPI or CPI value greater than 1 indicates that the project is ahead of schedule or under budget, respectively. An SPI or CPI value less than 1 indicates that the project is behind schedule or over budget, respectively1. In this question, the project manager notices that the SPI is 1.8 and the CPI is 0.1, which means that the project is ahead of schedule but over budget. This is a serious issue that needs to be addressed as soon as possible, as it may jeopardize the project viability and stakeholder satisfaction. The project manager should not ignore the project sponsor’s concern, as the project sponsor is the person who provides the financial resources and support for the project2. The project manager should also not assume that it is normal to spend more money in the design phase of a project, as this may indicate poor planning, estimation, or control of the project costs3. The project manager should not stop crashing the schedule, as this may affect the project scope, quality, or risk. The project manager should not use a resource-levelling technique, as this may delay the project completion and increase the project costs. The best option for the project manager is to manage the project sponsor closely and revise the project’s resource management plan to improve indicators. This means that the project manager should communicate frequently and transparently with the project sponsor, explain the reasons for the cost overrun, and seek their input and approval for any corrective actions. The project manager should also review and update the project’s resource management plan, which is the document that describes how the project resources will be estimated, acquired, managed, and controlled. The project manager should identify and implement strategies to reduce the project costs, such as optimizing the resource allocation, negotiating better rates, or eliminating unnecessary activities or resources. By managing the project sponsor closely and revising the project’s resource management plan, the project manager can improve the project performance indicators and increase the chances of delivering the project within the approved budget.

References:
1: PMBOK Guide, Chapter 7, Section 7.4.2.1, Page 267
2: PMBOK Guide, Chapter 13, Section 13.1.2.1, Page 518
3: 5 Essential Tips for Schedule Control in Project Management
4: PMBOK Guide, Chapter 6, Section 6.6.2.5, Page 215
5: PMBOK Guide, Chapter 6, Section 6.4.2.5, Page 201
6: Guide to Project Budgeting & Scheduling
7: PMBOK Guide, Chapter 9, Section 9.1.3.1, Page 313
8: How to Make a Project Budget: Project Budgeting Basics

A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.

How should the project manager respond?


A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced


B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework


C.

Record the issue in the issue log and escalate the conflict to the project sponsor for assistance


D.

Explain to the stakeholder that the stakelrolder engagement plan requires their attendance at all reviews





B.
  

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework



Explanation
Some of the other options are not appropriate because:

A. Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced. This option may compromise the quality and effectiveness of the reviews, as the stakeholder may miss important information, feedback, or decisions. It may also create a perception of low priority or commitment from the stakeholder, which can affect the trust and relationship with the project team3. The stakeholder engagement plan should reflect the optimal level of engagement for each stakeholder, not the minimum4.

C. Record the issue in the issue log and escalate the conflict to the project sponsor for assistance. This option may be too drastic and premature, as the issue may not be a serious conflict that requires escalation. Escalation should be used as a last resort, when the project manager cannot resolve the issue by themselves or with the stakeholder5. Escalation may also damage the rapport and communication with the stakeholder, as it may imply that the project manager is unable to handle the situation or respect the stakeholder’s perspective.

D. Explain to the stakeholder that the stakeholder engagement plan requires their attendance at all reviews. This option may sound too rigid and authoritative, as it does not acknowledge the stakeholder’s concern or provide any justification for the frequency of the reviews. It may also create a sense of resentment or resistance from the stakeholder, who may feel that they are being forced to comply with a plan that they do not agree with or understand. The stakeholder engagement plan should be a flexible and collaborative tool, not a rigid and imposed one4.

I hope this information helps you with your query. However, I suggest that you consult the official PMP and PBA reference materials and guides for more accurate and reliable information. Thank you for using Bing.

References:
1: Agile Manifesto Principles
2: Hybrid Project Management: What is it, Methodology & Software - Teamhood
3: Stakeholder Engagement: How to Keep Stakeholders Happy
4: Plan Stakeholder Engagement
5: Escalate Issues to Project Sponsor : [How to Escalate Project Issues Without Damaging Relationships] : [How to Deal with Difficult Stakeholders]

 

A technical manager newly appointed by the client, visits the project site to verify the project deliverables The technical manager feels that the project manager has not been providing enough information

What should the project manager do first to resolve this situation?


A.

Update the issue log and escalate to the project sponsor


B.

Identify the lack of information as a risk and update the risk register


C.

Schedule more frequent meetings with the technical manager.


D.

Review and update the stakeholder engagement plan





D.
  

Review and update the stakeholder engagement plan



The stakeholder engagement plan is a component of the project management plan that identifies the strategies and actions required to promote productive involvement of stakeholders in project decisions and activities1. The project manager should review and update the stakeholder engagement plan to address the needs and expectations of the newly appointed technical manager, who is a key stakeholder for the project. The project manager should also communicate with the technical manager to understand the information gaps and provide the necessary updates on the project deliverables. Updating the issue log and escalating to the project sponsor (option A) may not be the best first action, as it could create unnecessary conflict and damage the relationship with the client. Identifying the lack of information as a risk and updating the risk register (option B) is not appropriate, as the situation is not a potential uncertain event that could affect the project objectives, but rather a current issue that needs to be resolved. Scheduling more frequent meetings with the technical manager (option C) may help to improve the communication, but it does not address the root cause of the problem, which is the inadequate stakeholder engagement plan.

References:

A Guide to the Project Management Body of Knowledge (PMBOK® Guide) – Sixth Edition, Project Management Institute, Inc., 2017, p. 518.


Page 7 out of 32 Pages
Previous