While managing a project, a PM is assigned to work on a second project. The second project becomes more complex and monopolizes the PM's time. The PM learns that a similarly time-consuming project was executed previously in the organization. Which of the following actions should the PM take?


A. Perform a root cause analysis


B. Organize a stakeholder meeting


C. Escalate the issue to the CCB


D. Contact the PMO for assistance.





D.
  Contact the PMO for assistance.

Explanation: The project manager should contact the project management office (PMO) for assistance after learning that a similarly time-consuming project was executed previously in the organization. A PMO is a department or group within an organization that provides centralized guidance, governance, standards, best practices, resources, and oversight for project management activities. A PMO can help the project manager by providing access to historical data, lessons learned, templates, tools, methodologies, and expertise from previous projects that can be useful for planning and executing the current project.

A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?


A. RFB


B. RFQ


C. RFI


D. RFP





D.
  RFP

Explanation: A request for proposal (RFP) is the best document for the company to use in this scenario, because it is the most detailed and personalized type of request document. An RFP allows the company to specify the project scope, requirements, deliverables, evaluation criteria, and budget for the structured cabling installation, and to solicit proposals from various vendors that can meet those needs. An RFP also enables the company to compare the vendors based on their qualifications, experience, methodology, and pricing, and to select the best one for the project. An RFP is more suitable than an RFB, RFQ, or RFI, because those documents are less comprehensive and more generic, and they do not provide enough information for the company to make an informed decision. References = CompTIA Project+ Study Guide: Exam PK0-005, Third Edition, Chapter 5: Initiating the Project, page 1131; RFI, RFP, RFQ: Understanding the Differences2; Data Center Structured Cabling RFP Template3

During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?


A. Determine budget constraints.


B. Validate the business case.


C. Update the project charter.


D. Create a project schedule





C.
  Update the project charter.

Explanation: Update the project charter. Updating the project charter would be the next step for the project manager after identifying the project team during the project initiation phase. A project charter is a document that formally authorizes a project and defines its purpose, scope, objectives, deliverables, milestones, roles and responsibilities, assumptions, constraints, risks, budget, and timeline. A project charter can help to align the expectations and interests of all stakeholders involved in a project and provide direction and guidance for planning and executing the project.

Which of the following BEST illustrates how team members with different roles should interact on the team?


A. SOW


B. WBS


C. RACI


D. PERT





C.
  RACI

Explanation: RACI is a tool that best illustrates how team members with different roles should interact on the team. RACI is an acronym that stands for responsible, accountable, consulted, and informed. RACI is a type of responsibility assignment matrix (RAM) that defines and clarifies the roles and responsibilities of each team member for each task or activity in a project. RACI can help to improve communication, collaboration, and accountability among team members and avoid confusion, duplication, or conflicts3

During a brainstorming meeting, a project manager identifies multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals. Which of the following plans is the project manager creating?


A. Procurement


B. Communication


C. Quality assurance


D. Risk





C.
  Quality assurance

Explanation: The project manager is creating a quality assurance plan when identifying multiple techniques that will help the project team ensure confidence and alignment with the project scope and goals during a brainstorming meeting. A quality assurance plan is a plan that defines and documents the standards, criteria, methods, activities, and tools for ensuring and verifying that the quality requirements and expectations of a project are met. A quality assurance plan can help to improve the quality of the project processes and deliverables and prevent or reduce defects or errors.

As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?


A. Document the request in the change control log.


B. Communicate the change deployment.


C. Conduct an impact assessment.


D. Implement the change.





B.
  Communicate the change deployment.

Explanation: The project manager should communicate the change deployment next after updating the project plan with the newest project end date as a result of an approved change. Communicating the change deployment involves informing all relevant parties about when and how the change will be implemented and what are the expected outcomes and benefits. Communicating the change deployment can help to ensure alignment, readiness, and support for the change and avoid any confusion or resistance.

Because the project team lacks hands-on experience, the project manager has decided to involve a third-party vendor to complete the development of a product. Which of the following documents should the project manager expedite first?


A. RFI


B. RFP


C. RFQ


D. RFB





B.
  RFP

Explanation: When a project team lacks hands-on experience and decides to involve a third-party vendor for product development, the first document to expedite is a Request for Proposal (RFP). An RFP outlines the project requirements and asks potential vendors to submit proposals detailing how they would meet those requirements and at what cost. This allows the project manager to evaluate the capabilities and offerings of different vendors before making a decision.
References = CompTIA Project+ Certification Study Guide (PK0-005)

A team is working on a project that has different stages, such as initiation, planning, execution, and closure. Which of the following is this an example of?


A. Agile


B. Waterfall


C. Standard


D. Hybrid





B.
  Waterfall

A project manager has decided to outsource portions of a project and will conduct a separate procurement. In which of the following phases does this task occur?


A. Planning


B. Initiating


C. Controlling


D. Executing





A.
  Planning

Explanation: This answer is based on the understanding that outsourcing is a form of procurement, which is one of the knowledge areas in project management. Procurement involves acquiring goods and services from external sources to support the project objectives. According to the CompTIA Project+ Study Guide1, procurement activities occur mainly in the planning phase of the project, where the project manager identifies the project needs, defines the scope of work, evaluates the potential vendors, and prepares the procurement documents. The other options are not correct because:
Initiating is the phase where the project manager defines the project purpose, objectives, and deliverables, and obtains the project charter and stakeholder approval. Initiating does not involve procurement activities, although it may involve some preliminary research on the feasibility and availability of external resources.
Controlling is the phase where the project manager monitors and measures the project performance, compares it with the baseline, and implements corrective actions if needed. Controlling does involve some procurement activities, such as reviewing the vendor deliverables, managing the changes, and resolving the issues, but these are not the main tasks of procurement.
Executing is the phase where the project manager leads and directs the project team and other resources to complete the project work according to the plan. Executing does involve some procurement activities, such as selecting the vendor, signing the contract, and managing the relationship, but these are not the main tasks of procurement.

A project manager wants to be confident that the most crucial functions of a new software build work and that the software is ready for the next testing phase. Which of the following types of testing should be done?


A. Performance


B. Smoke


C. Regression


D. Unit





B.
  Smoke

Explanation: Smoke testing is a preliminary test to check whether the most essential functions of the software work correctly. It is often the first step in the testing phase and helps confirm that the build is stable enough for further testing. This aligns with CompTIA Project+ practices for software testing phases.

A project manager is meeting with business stakeholders to define the time frame for a go- live to occur without impacting business operations. Which of the following is the project manager working on?


A. Validation check


B. Downtime window schedule


C. Customer notifications


D. Risk analysis





B.
  Downtime window schedule

A project sponsor would like to develop a minimum viable product, but the requirements are not well defined. Which of the following should the project sponsor use?


A. Rational Unified Process


B. Waterfall


C. Agile


D. DevOps





C.
  Agile