Two developers are discussing the design solution for a particular feature. The meeting is taking longer than expected, and the parties have been unable to reach an agreement. The project manager decides to take a break and continue the meeting on another day. Which of the following techniques is the project manager using?


A. Avoiding


B. Smoothing


C. Forcing


D. Compromising





A.
  Avoiding

Explanation: Avoiding is a conflict resolution technique that involves postponing or withdrawing from a conflict situation. The project manager is using this technique by taking a break and continuing the meeting on another day, hoping that the conflict will resolve itself or become less important over time. This technique may be appropriate when the conflict is trivial, the potential damage is greater than the benefits, or more information is needed before making a decision.

Two project team members are assigned to set up new work areas and are disagreeing about the placement of hardware and peripherals at the end users' desks. The requirements do not specify where to place the items, just what is needed in each space. Which of the following should the project manager do to resolve the conflict?


A. Send out a survey to the potential end users to gather information about the best functional setup for work productivity.


B. Provide clear instructions based on personal preference and aesthetics for setup of the work areas.


C. Explain to team members that the placement of the items is not too important, as long as everything is connected and working.


D. Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.





D.
  Facilitate a meeting between team members to review the pros and cons of the different configurations so as to encourage an amicable solution.

Explanation: This answer is based on the best practice of conflict resolution in project management, which is to use a collaborative or problem-solving approach that seeks a win- win outcome for all parties involved12. By facilitating a meeting, the project manager can help the team members communicate effectively, understand each other’s perspectives, and find a mutually acceptable solution that meets the project requirements. This way, the project manager can also maintain team morale and cohesion, and avoid imposing a decision that may cause resentment or dissatisfaction among the team members3. References = CompTIA Project+ Certification Study Guide4, CompTIA Project+ Certification Exam Objectives5, How Do You Handle Conflict in Project Management?1, 7 Strategies for Conflict Resolution in Project Management2, The Conflict Resolution Skills Every Project Manager Needs3

A new project team started work three months ago. The team members are increasing their work productivity and are comfortable asking for help with tasks. Which of the following describes the current stage of the project team?


A. Performing


B. Adjourning


C. Forming


D. Norming





D.
  Norming

Explanation: The current stage of the project team is norming, which is the third stage of the five stages of team development. In this stage, the team members have resolved their conflicts and differences, and have established a sense of cohesion and collaboration. They are more productive, supportive, and cooperative, and they follow the agreed norms and rules of the team. They also communicate effectively and seek feedback and assistance from each other. The norming stage is preceded by the forming stage, where the team members get to know each other and the project goals, and the storming stage, where the team members experience disagreements and challenges. The norming stage is followed by the performing stage, where the team members work efficiently and autonomously towards the project outcomes, and the adjourning stage, where the team members complete the project and celebrate their achievements.

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?


A. Compromising


B. Forcing


C. Smoothing


D. Collaborating





C.
  Smoothing

A few weeks before a project is scheduled to be completed, the client asks to add a new feature to the product that is being developed. The project manager analyzes the project schedule and determines the feature can be implemented quite easily without affecting the completion date. Which of the following should the project manager do first?


A. Escalate the change to the CCB.


B. Review the requested change.


C. Document the change recommendations.


D. Validate the implementation of the requested change.





B.
  Review the requested change.

Explanation: The project manager should review the requested change first to assess its impact, feasibility, and alignment with the project objectives and scope. Reviewing the change will help the project manager to determine if the change is necessary, beneficial, and acceptable to the stakeholders. The project manager should also consider the risks, costs, and quality implications of the change before proceeding to the next steps of the change management process123. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 9: Project Change Management, p. 323; 5 Steps in the Change Management Process | HBS Online; 8 Steps for an Effective Change Management Process - Smartsheet

A project manager is assigned an initiative in a highly regulated industry that requires employees to safeguard certain pieces of PII. Which of the following is the best approach for the project manager to keep the information confidential?


A. Encryption


B. Multifactor authentication


C. Quality assurance


D. Password protection





A.
  Encryption

Someone claiming to be from a tax agency sent an email to a team member asking for access to the project repository. Which of the following BEST describes this scenario?


A. Social engineering


B. Phishing


C. Spoofing


D. Hacking





B.
  Phishing

Explanation: Phishing is a scenario where someone claiming to be from a legitimate organization sends an email or other message to a target person asking for sensitive information or access to a system or account. Phishing is a type of cyberattack that aims to trick the target into revealing personal or financial data or installing malware on their device. Phishing can compromise the security and privacy of the target and expose them to identity theft, fraud, or other malicious activities.

An opportunity emerged in the middle of a project life cycle. Which of the following is the BEST action for the project manager to take?


A. Exploit the risk.


B. Accept the risk.


C. Avoid the risk.


D. Transfer the risk.





A.
  Exploit the risk.

Explanation: The project manager should exploit the risk after an opportunity emerged in the middle of a project life cycle. Exploit is a risk response strategy that aims to increase the probability and/or impact of a positive risk or opportunity. Exploit can involve actions such as allocating more resources, changing the scope or schedule, or adding more features or benefits to the project deliverables. Exploit can help to ensure that the opportunity is realized and that the project gains more value or advantage from it3

A project is executed to migrate all data to a single system following the merger of two companies. The team validates that system performance will not be impacted. Which of the following did the team perform?


A. Regression testing


B. Smoke testing


C. Stress testing


D. Automation testing





C.
  Stress testing

A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?


A. Time and materials contract


B. Master service agreement


C. Fixed-price contract


D. Statement of work


E. Cost-plus agreement





A.
  Time and materials contract

Explanation: The project manager should put in place a time and materials contract before work begins for a third party that needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. A time and materials contract is a type of contract where the buyer pays the seller based on the actual time spent and materials used during the project. A time and materials contract is suitable for projects that have uncertain or variable scope, duration, or cost. A time and materials contract can provide flexibility and adaptability for both parties and allow them to adjust to changing requirements or circumstances.

A car manufacturer is presenting to three vendors the abilities and qualifications required to develop the last module of a data warehouse application. The manufacturer is emphasizing the technical skills necessary to complete the project on time and highlighting its current internal IT project. Which of the following best describes this activity?


A. Key stakeholder identification


B. Preliminary procurement


C. Solution design determination


D. Critical factor enlistment





B.
  Preliminary procurement

Which of the following provides the best justification for undertaking a project?


A. Scope statement


B. Business case


C. Sponsor request


D. Project charter





B.
  Business case