A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?


A. RFB


B. RFQ


C. RF


D. RFP





D.
  RFP

Explanation: An RFP (request for proposal) is a document that solicits proposals from potential vendors for a specific project or service. An RFP typically describes the project scope, requirements, evaluation criteria, and instructions for submitting proposals. An RFP is the best document for the company to use to obtain and compare information on cabling services and costs from various vendors, as it allows the company to evaluate the vendors’ qualifications, experience, approach, and pricing.

A project sponsor has asked for a log listing all the bugs identified within a specific project. Which of the following tools should the project manager provide to the sponsor?


A. Change log


B. Issue log


C. Risk register


D. Defect log





D.
  Defect log

Explanation: A defect log tracks and details all bugs and issues identified in a project. This log is essential for quality control and continuous improvement, as recommended by CompTIA Project+ guidelines on project monitoring and control.

Which of the following is a quantitative key performance indicator?


A. The project sponsor ranked the graphics of an application as four out of five.


B. The project implements the application in ten different geographical regions.


C. The workers complete tasks on average 25% faster using a new application.


D. The use of a multimedia interface appeals more to users under the age of 21.





C.
  The workers complete tasks on average 25% faster using a new application.

Explanation: Quantitative KPIs are measurable and based on numerical data. The statement about task completion time being 25% faster is quantitative, as it involves specific data that can be measured and tracked, as recommended by CompTIA Project+ for project performance evaluation.

After a migration was completed and a financial system was deployed, users have been unable to issue payment orders. Which of the following should be implemented?


A. Rollback plan


B. Release plan


C. Deployment plan


D. Contingency plan





A.
  Rollback plan

Explanation: A rollback plan is a part of the project management plan that defines how to revert the system to its previous state or baseline if the change or migration fails or causes unacceptable impacts1. A rollback plan is different from a contingency plan, which is a plan to deal with a specific risk event that may or may not occur2. A release plan and a deployment plan are not relevant to the scenario, as they are used to plan and execute the delivery and installation of the system, not to undo them. Therefore, the correct answer is A. Rollback plan.

Which of the following would most likely take place when a team reviews the backlog and presents the status of each task?


A. Sprint retrospective


B. Sprint review


C. Sprint planning


D. Daily Scrum





B.
  Sprint review

A client provides a project plan to the assigned project manager and suggests that the project manager and team just need to execute the plan. Upon further investigation, the document contains:
• Purpose
• Scope of work
• Location of work
• Period of performance
• Deliverables schedule
• Applicable standards
• Acceptance criteria
• Special requirements
• Payment schedule
Which of the following documents did the client provide to the project manager?


A. RFP


B. WBS


C. SLA


D. SOW





D.
  SOW

Explanation: The client provided a statement of work (SOW) to the project manager and suggested that the project manager and team just need to execute the plan. A SOW is a document that defines the scope, deliverables, schedule, and terms and conditions of a project or contract. A SOW typically includes information such as purpose, scope of work, location of work, period of performance, deliverables schedule, applicable standards, acceptance criteria, special requirements, and payment schedule. A SOW can help to establish a common understanding and agreement between the client and the service provider on what needs to be done and how it will be done.

A meeting agenda included the following items:

. Review the goals of the project.
. Review the progress of the project.
. Discuss if the project is ready to move forward.

Which of the following best describes this type of meeting?


A. Stand-up


B. Monthly status


C. Gap analysis


D. Gate review





D.
  Gate review

Explanation: A gate review is a type of meeting that evaluates the completion and quality of a project stage and decides whether the project can proceed to the next stage. A gate review is a formal governance step that involves reviewing the goals, progress, risks, deliverables, and benefits of the project, and discussing if the project is still aligned with the business strategy and stakeholder expectations. A gate review can have different outcomes, such as go, kill, hold, recycle, or conditional go, depending on the assessment of the project status and viability123. References = CompTIA Project+ Study Guide: Exam PK0-005, 3rd Edition, Chapter 9: Project Change Management, p. 323; Everything Project Managers Need To Know About Gate Reviews | monday.com Blog; Gate reviews: What to do and why you need them - Rebel’s Guide to Project Management; Gates and How to Operate Them - GenSight

A PM received feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. Which of the following is the MOST effective step for the PM to take to ensure clarity within the team?


A. Create a list of tasks and share it with the team.


B. Resend the scope of work to the team.


C. Review the Gantt chart weekly with the team.


D. Have the project sponsor meet with the team.





C.
  Review the Gantt chart weekly with the team.

Explanation: Reviewing the Gantt chart weekly with the team would be the most effective step for the project manager to take to ensure clarity within the team after receiving feedback from the project sponsor that the resources involved in the project are unsure of their daily activities. A Gantt chart is a graphical tool that shows the schedule of a project, including the start and end dates, durations, dependencies, milestones, and progress of each task or activity. Reviewing the Gantt chart weekly with the team can help to clarify their roles and responsibilities, assign tasks and deadlines, track and report their status and performance, identify and resolve any issues or risks, and keep them aligned and engaged with the project goals.

A team member identifies a critical issue in production. Which of the following should the project manager apply?


A. Compliance check


B. Release plan


C. Rollback plan


D. Validation check





C.
  Rollback plan

Two team members have a minor disagreement on how a task should be performed. The project manager plans to meet with the team members to discuss the matter. Which of the following techniques should the project manager use to emphasize the areas of agreement and downplay the opposing views?


A. Compromising


B. Forcing


C. Smoothing


D. Collaborating





C.
  Smoothing

Explanation: Smoothing is a conflict resolution technique that involves minimizing or ignoring the differences between the parties and focusing on the common interests or goals1. It is often used when the conflict is not very important or when there is a need to maintain harmony and relationships2. By using smoothing, the project manager can reduce the tension and stress caused by the disagreement and encourage the team members to cooperate and work together. Smoothing is different from compromising, which involves finding a middle ground or a trade-off that partially satisfies both parties; forcing, which involves imposing one’s own solution or decision on the other party; and collaborating, which involves finding a win-win solution that fully satisfies both parties3.

The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?


A. External


B. Internal


C. Mandatory


D. Discretionary





C.
  Mandatory

Explanation: The dependency between software installation and desktop installation is a mandatory dependency. A mandatory dependency is a type of dependency that is inherent in the nature or logic of the work and cannot be avoided or changed. It is also known as a hard dependency or a hard logic dependency. A mandatory dependency means that one task must be completed before another task can start or finish. For example, software installation can only start after desktop installation is finished. The dependency between desktop installation and software installation represents a mandatory dependency. A mandatory dependency is a type of task dependency that is inherent in the nature of the work being performed. In this case, software installation cannot begin until desktops are installed and powered on, and therefore, the dependency is mandatory.

A project manager is currently meeting with a vendor who completed the project work. All invoices associated with the project have been paid. Which of the following best describes the project manager's objective for the vendor meeting?


A. Reassigning resources


B. Removing access


C. Closing contracts


D. Evaluating the project





C.
  Closing contracts

Explanation: Closing contracts involves finalizing any remaining contractual obligations and formally closing out the relationship with the vendor. CompTIA Project+ emphasizes this as part of the project closure phase to ensure all legal and financial aspects are complete.