Topic 1, Part 1
In which of the following ADM Phases do building blocks become implementation-specific?
A.
Phase A
B.
Phase B
C.
Phase C
D.
Phase D
E.
Phase E
Phase E
Which of the following best describes an approach for adapting the ADM in the situation where
business principles dictate that a packaged solution be used?
A.
Completion of the Business Architecture should follow the Information Systems Architecture
B.
Create an Architecture Vision and then a detailed Business Architecture
C.
Produce a "cut-down" version of the ADM suitable to the resources available
D.
Tailor the ADM in conjunction with another architecture framework that has deliverables specific
to the vertical sector
E.
Tailor the ADM to reflect the relationships with, and dependencies on other management
processes within the organization
Completion of the Business Architecture should follow the Information Systems Architecture
Which Architecture domain is recommended to be the first architecture work undertaken in the
ADM cycle?
A.
Application Architecture
B.
Business Architecture
C.
Data Architecture
D.
Technology Architecture
Business Architecture
Complete the sentence. According to TOGAF, all of the following are responsibilities of an
Architecture Board, except ______________________.
A.
Ensuring consistency between sub-architectures
B.
Ensuring flexibility of the enterprise architecture to meet business needs
C.
Improving the maturity of the organization's architecture discipline
D.
Monitoring of architecture contracts
E.
Preparing architecture review reports
Preparing architecture review reports
Which section of the TOGAF document contains a structured metamodel for architectural
artifacts?
A.
Part II: Architecture Development Method
B.
Part III: ADM Guidelines and Techniques
C.
Part IV: Architecture Content Framework
D.
Part VI: TOGAF Reference Models
E.
Part VII: Architecture Capability Framework
Part IV: Architecture Content Framework
Which of the following statements about TOGAF Building Blocks is true?
A.
A good Building Block should not be composed of other Building Blocks
B.
Architecture Building Blocks should be first selected in Phase D
C.
Building Block specifications should be loosely coupled to implementation
D.
Custom developments are known as Architecture Building Blocks
Building Block specifications should be loosely coupled to implementation
According to TOGAF, which of the following is a characteristic of a Foundation Architecture?
A.
It contains only solution building blocks
B.
It contains business functions and processes specific to a particular industry sector
C.
It contains building blocks and their corresponding standards
D.
It includes a model of application components and application services software, including
brokering applications
E.
It includes models for common high-level business functions, such as supply chain
management
It contains building blocks and their corresponding standards
Complete the sentence. TOGAF covers the development of four architecture domains, Business,
Data, Technology and ___________.
A.
Application
B.
Capability
C.
Segment
D.
Transition
E.
Vision
Application
Which of the following describes an objective of Phase G: Implementation Governance?
A.
Finalize the Implementation and Migration Plan
B.
Establish the recourses for architecture governance
C.
Ensure conformance for the target architecture
D.
Operate the governance framework
E.
Develop the Target Technology Architecture
Ensure conformance for the target architecture
Which of the following best describes the purpose of the Statement of Architecture Work?
A.
It contains an assessment of the current architecture requirements
B.
It defines the scope and approach to complete an architecture project
C.
It is sent from the sponsor and triggers the start of an architecture development cycle
D.
It provides a high-level aspirational view of the end architecture project
E.
It provides a schedule for implementation of the target architecture
It defines the scope and approach to complete an architecture project
Which of the following describes en objective of the Preliminary Phase?
A.
Develop a vision of the proposed enterprise architecture
B.
Document the baseline architecture
C.
Obtain approval for the Statement of Architecture Work
D.
Operate the governance framework
E.
Select and implement tools
Select and implement tools
In which part of the ADM cycle do building block gaps become associated with work packages that
will address the gaps?
A.
Preliminary Phase and Phase A
B.
Phases B, C, and D
C.
Phase E
D.
Phase F
E.
Phases G and H
Phase E