Topic 1, Volume A
Which process involves developing an approximation of the monetary resources needed to
complete project activities?
A.
Estimate Costs
B.
Control Costs
C.
Determine Budget
D.
Plan Cost Management
Estimate Costs
Which tool or technique is used in the Develop Project Management Plan process?
A.
Pareto diagram
B.
Performance reporting
C.
SWOT analysis
D.
Expert judgment
Expert judgment
Lessons learned are created and project resources are released in which Process Group?
A.
Planning
B.
Executing
C.
Closing
D.
Initiating
Closing
When should quality planning be performed?
A.
While developing the project charter
B.
In parallel with the other planning processes
C.
As part of a detailed risk analysis
D.
As a separate step from the other planning processes
In parallel with the other planning processes
A key benefit of the Manage Communications process is that it enables:
A.
The best use of communication methods.
B.
An efficient and effective communication flow.
C.
Project costs to be reduced.
D.
The best use of communication technology.
An efficient and effective communication flow.
The ways in which the roles and responsibilities, reporting relationships, and staffing management
will be addressed and structured within a project is described in the:
A.
Human resource management plan.
B.
Activity resource requirements.
C.
Personnel assessment tools,
D.
Multi-criteria decision analysis.
Human resource management plan.
The process of identifying and documenting relationships among the project activities is known as:
A.
Control Schedule.
B.
Sequence Activities.
C.
Define Activities.
D.
Develop Schedule.
Sequence Activities.
Conditions that are not under the control of the project team that influence, direct, or constrain a
project are called:
A.
Enterprise environmental factors
B.
Work performance reports
C.
Organizational process assets
D.
Context diagrams
Enterprise environmental factors
The organization's perceived balance between risk taking and risk avoidance is reflected in the
risk:
A.
Responses
B.
Appetite
C.
Tolerance
D.
Attitude
Responses
An output of the Manage Stakeholder Engagement process is:
A.
change requests
B.
enterprise environmental factors
C.
the stakeholder management plan
D.
the change log
change requests
Which process numerically analyzes the effect of identified risks on overall project objectives?
A.
Plan Risk Management
B.
Plan Risk Responses
C.
Perform Quantitative Risk Analysis
D.
Perform Qualitative Risk Analysis
Perform Quantitative Risk Analysis
An input to the Plan Procurement Management process is:
A.
Source selection criteria.
.
B.
Market research.
C.
A stakeholder register.
D.
A records management system
A stakeholder register.