Topic 1, Volume A
Sending letters, memos, reports, emails, and faxes to share information is an example of which
type of communication?
A.
Direct
B.
Interactive
C.
Pull
D.
Push
Push
Which earned value management (EVM) metric is a measure of the cost efficiency of budgeted
resources expressed as a ratio of earned value (EV) to actual cost (AC) and is considered a
critical EVM metric?
A.
Cost variance (CV)
B.
Cost performance index (CPI)
C.
Budget at completion (BAC)
D.
Variance at completion (VAC)
Cost performance index (CPI)
Which process involves defining, preparing, and coordinating all subsidiary plans and integrating
them into a comprehensive plan?
A.
Direct and Manage Project Work
B.
Develop Project Management Plan
C.
Plan Quality Management
D.
Monitor and Control Project Work
Develop Project Management Plan
Inputs to the Plan Schedule Management process include:
A.
Organizational process assets and the project charter,
B.
Enterprise environmental factors and schedule tools.
C.
Time tables and Pareto diagrams.
D.
Activity attributes and resource calendars.
Organizational process assets and the project charter,
A strengths, weaknesses, opportunities, and threats (SWOT) analysis is a tool or technique used
in which process?
A.
Identify Risks
B.
Control Risks
C.
Perform Quantitative Risk Analysis
D.
Perform Qualitative Risk Analysis
Identify Risks
Which Knowledge Area involves identifying the people, groups, or organizations that may be
impacted by or impact a project?
A.
Project Risk Management
B.
Project Human Resource Management
C.
Project Scope Management
D.
Project Stakeholder Management
Project Stakeholder Management
Which input to Collect Requirements is used to identify stakeholders who can provide information
on requirements?
A.
Stakeholder register
B.
Scope management plan
C.
Stakeholder management plan
D.
Project charter
Stakeholder register
Which process identifies whether the needs of a project can best be met by acquiring products,
services, or results outside of the organization?
A.
Plan Procurement Management
B.
Control Procurements
C.
Collect Requirements
D.
Plan Cost Management
Plan Procurement Management
Which tool or technique is used to manage change requests and the resulting decisions?
A.
Change control tools
B.
Expert judgment
C.
Delphi technique
D.
Change log
Change control tools
The planned work contained in the lowest level of work breakdown structure (WBS) components is
known as:
A.
Work packages.
B.
Accepted deliverables.
C.
The WBS dictionary.
D.
The scope baseline.
Work packages.
In which Knowledge Area is the project charter developed?
A.
Project Cost Management
B.
Project Scope Management
C.
Project Time Management
D.
Project Integration Management
Project Integration Management
The ability to influence cost is greatest during which stages of the project?
A.
Early
B.
Middle
C.
Late
D.
Completion
Early
Page 7 out of 66 Pages |
Previous |