CAPM Practice Test Questions

785 Questions


Topic 1, Volume A

Which item is an example of personnel assessment?


A.

Resource calendar


B.

Tight matrix


C.

Team-building activity


D.

Focus group





The Plan Stakeholder Management process belongs to which Process Group?


A.

Executing


B.

Initiating


C.

Planning


D.

Monitoring and Controlling





Which input to the Manage Stakeholder Engagement process provides guidance on how
stakeholders can best be involved in a project?


A.

Feedback analysis


B.

Stakeholder analysis


C.

Communication management plan


D.

Stakeholder management plan





A method of obtaining early feedback on requirements by providing a working model of the
expected product before actually building is known as:


A.

Benchmarking.


B.

Context diagrams.


C.

Brainstorming.


D.

Prototyping.





Which stakeholder classification model groups stakeholders based on their level of authority and
their active involvement in the project?


A.

Power/influence grid


B.

Power/interest grid


C.

Influence/impact grid


D.

Salience model





Which Plan Schedule Management tool or technique may involve choosing strategic options to
estimate and schedule the project?


A.

Facilitation techniques


B.

Expert judgment


C.

Analytical techniques


D.

Variance analysis





The process of estimating the type and quantity of material, human resources, equipment, or
supplies required to perform each activity is known as:


A.

Collect Requirements.


B.

Conduct Procurements.


C.

 Estimate Activity Durations.


D.

Estimate Activity Resources





Which basic quality tool is most useful when gathering attributes data in an inspection to identify
defects?


A.

Control charts


B.

Pareto diagrams


C.

 Ishikavva diagrams


D.

Checksheets





Which input to the Identify Stakeholders process provides information about internal or external
parties related to the project?


A.

Procurement documents


B.

Communications plan


C.

Project charter


D.

Stakeholder register





The Identify Stakeholders process is found in which Process Group?


A.

Initiating


B.

Monitoring and Controlling


C.

Planning


D.

Executing





An input to Develop Project Charter is a/an:


A.

 Business case.


B.

Activity list.


C.

Project management plan.


D.

 Cost forecast.





Which item is a formal proposal to modify any document, deliverable, or baseline?


A.

Change request


B.

Requirements documentation


C.

Scope baseline


D.

Risk urgency assessment