CAPM Practice Test Questions

785 Questions


Topic 1, Volume A

Which group is formally chartered and responsible for reviewing, evaluating, approving, delaying,
or rejecting changes to the project and for recording and communicating decisions?


A.

Project team


B.

Focus group


C.

 Change control board


D.

Project stakeholders





C.
  

 Change control board



Plan Schedule Management is a process in which Knowledge Area?


A.

Project Scope Management


B.

Project Human Resource Management


C.

Project Integration Management


D.

Project Time Management





D.
  

Project Time Management



An output of the Validate Scope process is:


A.

A requirements traceability matrix.


B.

The scope management plan.


C.

Work performance reports.


D.

Change requests.





D.
  

Change requests.



The Perform Integrated Change Control process occurs in which Process Group?


A.

Initiating


B.

Executing


C.

Monitoring and Controlling


D.

Planning





C.
  

Monitoring and Controlling



Which input to the Plan Risk Management process provides information on high-level risks?


A.

Project charter


B.

Enterprise environmental factors


C.

Stakeholder register


D.

Organizational process assets





A.
  

Project charter



Which input may influence quality assurance work and should be monitored within the context of a
system for configuration management?


A.

Work performance data


B.

Project documents


C.

Scope baseline


D.

Requirements documentation





B.
  

Project documents



Change requests are processed for review and disposition according to which process?


A.

Control Quality


B.

Control Scope


C.

Monitor and Control Project Work


D.

Perform Integrated Change Control





D.
  

Perform Integrated Change Control



The review of a sellers progress toward achieving the goals of scope and quality within cost and
schedule compared to the contract is known as:


A.

Work performance information.


B.

Inspections and audits.


C.

Payment systems.


D.

Procurement performance reviews.





D.
  

Procurement performance reviews.



The iterative and interactive nature of the Process Groups creates the need for the processes in
which Knowledge Area?


A.

Project Communications Management


B.

Project Integration Management


C.

Project Risk Management


D.

Project Scope Management





B.
  

Project Integration Management



Market conditions and published commercial information are examples of which input to the
Estimate Costs process?


A.

Scope baseline


B.

Organizational process assets


C.

Enterprise environmental factors


D.

Risk register





C.
  

Enterprise environmental factors



An output of the Develop Project Team process is:


A.

Organizational process assets.


B.

Enterprise environmental factors updates.


C.

Project staff assignments.


D.

Organizational charts and position descriptions.





B.
  

Enterprise environmental factors updates.



The process of confirming human resource availability and obtaining the team necessary to
complete project activities is known as:


A.

Plan Human Resource Management.


B.

Acquire Project Team.


C.

Manage Project Team.


D.

Develop Project Team.





B.
  

Acquire Project Team.




Page 4 out of 66 Pages
Previous