Topic 1, Volume A
Which item is an input to the Define Activities process?
A.
Schedule data
B.
Activity list
C.
Risk register
D.
Scope baseline
Scope baseline
When alternative dispute resolution (ADR) is necessary, which tool or technique should be
utilized?
A.
Interactive communication
B.
Claims administration
C.
Conflict management
D.
Performance reporting
Claims administration
Which quality management and control tool is useful in visualizing parent-to-child relationships in
any decomposition hierarchy that uses a systematic set of rules that define a nesting relationship?
A.
Interrelationship digraphs
B.
Tree diagram
C.
Affinity diagram
D.
Network diagram
Tree diagram
The only Process Group that comprises processes that typically occur from the beginning to the
end of the project life cycle is:
A.
Planning.
B.
Executing,
C.
Monitoring and Controlling.
D.
Closing.
Monitoring and Controlling.
Organizational theory is a tool used in which Project Human Resource Management process?
A.
Manage Project Team
B.
Acquire Project Team
C.
Develop Project Team
D.
Plan Human Resource Management
Plan Human Resource Management
Which tools or techniques are used in the Plan Schedule Management process?
A.
Benchmarking, expert judgment, and analytical techniques
B.
Statistical sampling, benchmarking, and meetings
C.
Negotiations, pre-assignment, and multi-criteria decision analysis
D.
Expert judgment, analytical techniques, and meetings
Expert judgment, analytical techniques, and meetings
A project manager is appointed full-time to a project and is given full-time administrative staff and
full-time project team members. This situation describes which type of organizational structure?
A.
Projectized
B.
Weak matrix
C.
Functional
D.
Balanced matrix
Projectized
A project charter is an output of which Process Group?
A.
Executing
B.
Planning
C.
Initiating
D.
Closing
Initiating
Which tool or technique is effective in a project in which the deliverable is not a service or result?
A.
Inspection
B.
Variance analysis
C.
Decomposition
D.
Product analysis
Product analysis
An element of the project scope statement is:
A.
Acceptance criteria.
B.
A stakeholder list.
C.
A summary budget,
D.
High-level risks
Acceptance criteria.
Which document describes the necessary information to determine if a project is worth the
required investment?
A.
Cost baseline
B.
Service level agreement
C.
Memorandum of understanding
D.
Business case
Business case
Which process involves monitoring the status of the project to update the project costs and
managing changes to the cost baseline?
A.
Estimate Costs
B.
Control Costs
C.
Determine Budget
D.
Plan Cost Management
Control Costs
Page 3 out of 66 Pages |