Topic 3, Volume C
When an activity cannot be estimated with a reasonable degree of confidence, the work within the
activity is decomposed into more detail using which type of estimating?
A.
Bottom-up
B.
Parametric
C.
Analogous
D.
Three-point
Bottom-up
Definitions of probability and impact, revised stakeholder tolerances, and tracking are components
of which subsidiary plan?
A.
Cost management plan
B.
Quality management plan
C.
Communications management plan
D.
Risk management plan
Risk management plan
Project or phase closure guidelines or requirements, historical information, and the lessons
learned knowledge base are examples of which input to the Close Project or Phase process?
A.
Organizational process assets
B.
A work breakdown structure
C.
The project management plan
D.
Enterprise environmental factors-
Organizational process assets
The project manager notes that stakeholders are aware of the project and potential impacts and
are actively engaged in ensuring that the project is a success. The engagement level of the
stakeholders should be classified as:
A.
Supportive
B.
Leading
C.
Neutral
D.
Resistant
Leading
Which of the following is a narrative description of products, services, or results to be delivered by
a project?
A.
Project statement of work
B.
Business case
C.
Accepted deliverable
D.
Work performance information
Project statement of work
A project manager seeking insight on previous stakeholder management plans and their
effectiveness should evaluate:
A.
Historical information and the lessons-learned database.
B.
Historical information and the stakeholder register.
C.
Organizational process assets and the lessons-learned database.
D.
Project documents and historical information
Historical information and the lessons-learned database.
Projects are undertaken by an organization to support the:
A.
Product performance.
B.
Budget process.
C.
Collective capabilities.
D.
Organizational strategy
Organizational strategy
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur
is very high (0.80)?
A.
0.45
B.
0.56
C.
0.70
D.
1.36
0.70
Which of the seven basic quality tools is especially useful for gathering attributes data while
performing inspections to identify defects?
A.
Histograms
B.
Scatter diagrams
C.
Flowcharts
D.
Checksheets
Checksheets
The most commonly used type of precedence relationship in the precedence diagramming method
(PDM) is:
A.
start-to-start (SS)
B.
start-to-finish (SF)
C.
finish-to-start (FS)
D.
finish-to-finish (FF)
finish-to-start (FS)
Work performance information and cost forecasts are outputs of which Project Cost Management
process?
A.
Estimate Costs
B.
Plan Cost Management
C.
Determine Budget
D.
Control Costs
Control Costs
Which technique should a project manager use in a situation in which a collaborative approach to
conflict management is not possible?
A.
Coaching
B.
Avoidance
C.
Consensus
D.
Influencing
Avoidance
Page 27 out of 66 Pages |