Topic 3, Volume C
An input of the Plan Procurement Management process is:
A.
Make-or-buy decisions.
B.
Activity cost estimates.
C.
Seller proposals.
D.
Procurement documents.
Activity cost estimates.
Outputs of the Control Communications process include:
A.
expert judgment and change requests
B.
work performance information and change requests
C.
project management plan updates and work performance information
D.
issue logs and organizational process assets updates
work performance information and change requests
Which organizational process assets update is performed during the Close Procurements
process?
A.
Procurement audit
B.
Lessons learned
C.
Performance reporting
D.
Payment requests
Lessons learned
The individual or group that provides resources and support for a project and is accountable for
success is the:
A.
sponsor
B.
customer
C.
business partners
D.
functional managers
sponsor
A measure of cost performance that is required to be achieved with the remaining resources in
order to meet a specified management goal and is expressed as the ratio of the cost needed for
finishing the outstanding work to the remaining budget is known as the:
A.
budget at completion (BAC)
B.
earned value management (EVM)
C.
to-complete performance index
D.
cost performance index
to-complete performance index
A collection of projects managed as a group to achieve strategic objectives is referred to as a:
A.
plan
B.
process
C.
program
D.
portfolio
portfolio
Sharing good practices introduced or implemented in similar projects in the organization and/or
industry is an example of:
A.
quality audits
B.
process analysis
C.
statistical sampling
D.
benchmarking
quality audits
Which Process Group's purpose is to track, review, and regulate the progress and performance of
the project; identify any areas in which changes to the plan are required; and initiate the
corresponding changes?
A.
Monitoring and Controlling
B.
Initiating
C.
Planning
D.
Executing
Monitoring and Controlling
The formal and informal interaction with others in an organization industry, or professional
environment is known as:
A.
negotiation
B.
organizational theory
C.
meeting
D.
networking
networking
Which process is included in the Project Integration Management Knowledge Area?
A.
Manage Project Team
B.
Collect Requirements
C.
Sequence Activities
D.
Direct and Manage Project Work
Direct and Manage Project Work
The process of identifying and documenting the specific actions to be performed to produce the
project deliverables is known as:
A.
Define Activities.
B.
Sequence Activities.
C.
Define Scope.
D.
Control Schedule.
Define Activities.
Which document includes the project scope, major deliverables, assumptions, and constraints?
A.
Project charter
B.
Project scope statement
C.
Scope management plan
D.
Project document updates
Project scope statement
Page 26 out of 66 Pages |