CAPM Practice Test Questions

785 Questions


Topic 2, Volume B

Which enterprise environmental factors may influence Plan Schedule Management?


A.

Cultural views regarding time schedules and professional and ethical behaviors


B.

Historical information and change control procedures


C.

Risk control procedures and the probability and impact matrix


D.

 Resource availability and organizational culture and structure





D.
  

 Resource availability and organizational culture and structure



Which type of dependency used in the Sequence Activities process is sometimes referred to as
preferred logic, preferential logic, or soft logic?


A.

Internal


B.

External


C.

Discretionary


D.

Mandatory





C.
  

Discretionary



When the business objectives of an organization change, project goals need to be:


A.

realigned.


B.

 performed.


C.

 improved.


D.

controlled.





A.
  

realigned.



Which of the Perform Quality Assurance tools and techniques may enhance the creation of the
work breakdown structure (VVBS) to give structure to the decomposition of the scope?


A.

Activity network diagrams


B.

Affinity diagrams


C.

Matrix diagrams


D.

Interrelationship digraphs





B.
  

Affinity diagrams



A project manager who communicates to the project team though email is using which type of
communication?


A.

Formal


B.

Informal r


C.

Horizontal


D.

Unofficial





B.
  

Informal r



An input to the Perform Integrated Change Control process is:


A.

expert judgment


B.

seller proposals


C.

 the project charter


D.

the project management plan





D.
  

the project management plan



Which tool or technique is required in order to determine the project budget?


A.

Cost of quality


B.

Historical relationships


C.

Project management software


D.

Forecasting





B.
  

Historical relationships



Requirements documentation will typically contain at least:


A.

Stakeholder requirements, staffing requirements, and transition requirements.


B.

Business requirements, the stakeholder register, and functional requirements.



C.

Stakeholder impact, budget requirements, and communications requirements.


D.

Business objectives, stakeholder impact, and functional requirements





D.
  

Business objectives, stakeholder impact, and functional requirements



Which process involves the creation of a document that provides the project manager with the
authority to apply resources to a project?


A.

Define Activities


B.

Direct and Manage Project Work


C.

Develop Project Management Plan


D.

 Develop Project Charter





D.
  

 Develop Project Charter



The stakeholder register is an output of:


A.

Identify Stakeholders.


B.

Plan Stakeholder Management.


C.

Control Stakeholder Engagement.


D.

Manage Stakeholder Engagement.





A.
  

Identify Stakeholders.



Which type of manager is assigned by the performing organization to lead the team that is
responsible for achieving the project objectives?


A.

Program


B.

Functional


C.

Project


D.

Portfolio





C.
  

Project



The approaches, tools, and data sources that will be used to perform risk management on a
project are determined by the:


A.

Methodology


B.

Risk category


C.

Risk attitude


D.

Assumption analysis





A.
  

Methodology




Page 25 out of 66 Pages
Previous