Topic 2, Volume B
Whose approval may be required for change requests after change control board (CCB) approval?
A.
Functional managers
B.
Business partners
C.
Customers or sponsors
D.
Subject matter experts
Customers or sponsors
The primary benefit of the Plan Schedule Management process is that it:
A.
provides guidance to identify time or schedule challenges within the project.
B.
tightly links processes to create a seamless project schedule.
C.
guides how the project schedule will be managed throughout the project.
D.
creates an overview of all activities broken down into manageable subsections.
guides how the project schedule will be managed throughout the project.
Grouping the stakeholders based on their level of authority and their level of concern regarding
project outcomes describes which classification model for stakeholder analysis?
A.
Influence/impact grid
B.
Power/influence grid
C.
Power/interest grid
D.
Salience model
Power/interest grid
Variance and trend analysis is a tool and technique used in which process?
A.
Perform Qualitative Risk Analysis
B.
Perform Quantitative Risk Analysis
C.
Control Risks
D.
Plan Risk Responses
Control Risks
An intentional activity to modify a nonconforming product or product component is called:
A.
defect repair
B.
work repair
C.
corrective action
D.
preventive action
defect repair
Which quality tool incorporates the upper and lower specification limits allowed within an
agreement?
A.
Control chart
B.
Flowchart
C.
Checksheet
D.
Pareto diagram
Control chart
Analytical techniques are a tool and technique of which process in Project Procurement
Management?
A.
Plan Procurement Management
B.
Control Procurements
C.
Conduct Procurements
D.
Close Procurements
Conduct Procurements
The process of obtaining seller responses, selecting a seller, and awarding a contract is called:
A.
Close Procurements.
B.
Control Procurements.
C.
Plan Procurements.
D.
Conduct Procurements.
Conduct Procurements.
Impacts to other organizational areas, levels of service, and acceptance criteria are typical
components of which document?
A.
Business case
B.
Work breakdown structure
C.
Requirements documentation
D.
Risk register
Requirements documentation
Which Process Group includes the Manage Stakeholder Engagement process?
A.
Executing
B.
Planning
C.
Monitoring and Controlling
D.
Initiating
Executing
Funding limit reconciliation is a tool and technique of which Project Cost Management process?
A.
Estimate Costs
B.
Control Costs
C.
Plan Cost Management
D.
Determine Budget
Determine Budget
In complex projects/ initiating processes should be completed:
A.
Within a work package.
B.
In each phase of the project.
C.
To estimate schedule constraints.
D.
To estimate resource allocations
In each phase of the project.