Topic 2, Volume B
Which Manage Communications tool or technique focuses on identifying and managing barriers?
A.
Communication methods
B.
Information technology
C.
Communication models
D.
Information management systems
Communication models
Which type of organizational structure is displayed in the diagram provided?
A.
Balanced matrix
B.
Projectized
C.
Strong matrix
D.
Functional
Projectized
Outputs of the Control Communications process include
A.
expert judgment and change requests
B.
work performance information and change requests.
C.
organizational process asset updates and an issue log.
D.
project management plan updates and an issue log.
work performance information and change requests.
In the Plan Procurement Management process, which source selection criteria analyzes if the
seller's proposed technical methodologies, techniques, solutions, and services meet the
procurement documents requirements?
A.
Technical approach
B.
Technical capability
C.
Business size and type
D.
Production capacity and interest
Technical approach
Stakeholder communication requirements should be included as a component of:
A.
enterprise environmental factors
B.
organizational process assets
C.
the project management plan
D.
the stakeholder register
the project management plan
Which element does a project charter contain?
A.
Management reserves
B.
Work breakdown structure
C.
Stakeholder list
D.
Stakeholder register
Stakeholder list
The following is a network diagram for a project
What is the critical path for the project?
A.
A-B-C-F-G-I
B.
A-B-C-F-H-I
C.
A-D-E-F-G-I
D.
A-D-E-F-H-I
A-B-C-F-G-I
The following is a network diagram for a project
How many possible paths are identified for this project?
A.
3
B.
4
C.
6
D.
7
4
The following is a network diagram for a project.
The free float for Activity H is how many days?
A.
4
B.
5
C.
10
D.
11
4
Every project creates a unique product, service, or result that may be:
A.
tangible
B.
targeted
C.
organized
D.
variable
tangible
Correlated and contextualized information on how closely the scope is being maintained relative to
the scope baseline is contained within:
A.
project documents updates.
B.
project management plan updates.
C.
change requests.
D.
work performance information.
work performance information.
The most appropriate project life cycle model for an environment with a high level of change and
extensive stakeholder involvement in projects is:
A.
adaptive
B.
reflexive
C.
predictive
D.
iterative
adaptive