A benefit of using virtual teams in the Acquire Project Team process is the reduction of the:
A.
cultural differences of team members
B.
possibility of communication misunderstandings
C.
costs associated with travel
D.
costs associated with technology
costs associated with travel
Those who enter into a contractual agreement to provide services necessary for a project are:
A.
buyers
B.
sellers
C.
business partners
D.
product users
sellers
Project managers who lead by example and follow through on the commitments they make
demonstrate the key interpersonal skill of:
A.
influencing
B.
leadership
C.
motivation
D.
coaching
influencing
Which items are an output of the Perform Integrated Change Control process?
A.
Work performance reports
B.
Accepted deliverables
C.
Project management plan updates
D.
Organizational process assets
Project management plan updates
Which term describes an assessment of correctness?
A.
Accuracy
B.
Precision
C.
Grade
D.
Quality
Accuracy
The cost baseline and project funding requirements are outputs of which process in Project Cost
Management?
A.
Estimate Costs
B.
Control Costs
C.
Plan Cost Management
D.
Determine Budget
Determine Budget
The Project Human Resource Management process that involves confirming human resource
availability and obtaining the team necessary to complete project activities is:
A.
Acquire Project Team.
B.
Plan Human Resource Management.
C.
Manage Project Team.
D.
Develop Project Team.
Acquire Project Team.
At the start of a typical project life cycle, costs are:
A.
low, peak as work is carried out, and drop as the project nears the end.
B.
low, become steady as work is carried out, and increase as the project nears the end.
C.
high, drop as work is carried out, and increase as the project nears the end.
D.
high, become low as work is carried out, and drop as the project nears the end
low, peak as work is carried out, and drop as the project nears the end.
Success is measured by benefits realization for a:
A.
strategic plan
B.
project
C.
portfolio
D.
program
portfolio
Organizational process assets, a lessons-learned database, and historical information are all
inputs to which process?
A.
Plan Cost Management
B.
Plan Scope Management
C.
Plan Stakeholder Management
D.
Plan Schedule Management
Plan Stakeholder Management
A project team member agrees to change a project deliverable after a conversation with an
external stakeholder. It is later discovered that the change has had an adverse effect on another
deliverable. This could have been avoided if the project team had implemented:
A.
Quality assurance.
B.
A stakeholder management plan.
C.
Project team building.
D.
Integrated change control.
Integrated change control.
The process of defining how the project scope will be validated and controlled is known as:
A.
Define Scope.
B.
Develop Project Management Plan.
C.
Plan Scope Management.
D.
Plan Quality Management.
Plan Scope Management.