Plan Communications Management develops an approach and plan for project communications
based on stakeholders' needs and requirements and:
A.
Available organizational assets
B.
Project staff assignments
C.
Interpersonal skills
D.
Enterprise environmental factors
Available organizational assets
Perform Integrated Change Control is the process of:
A.
Reviewing, approving, and managing all change requests
B.
Facilitating change management, manuals, or automation tools
C.
Comparing actual results with planned results in order to expand or change a project
D.
Documenting changes according to the change control system by the change control board
Reviewing, approving, and managing all change requests
When painting a bedroom, preparing the walls can be done while the paint is being chosen. This is
an example of a:
A.
lead
B.
lag
C.
mandatory dependency
D.
internal dependency
lead
Which action is included in the Control Costs process?
A.
Identify how the project costs will be planned, structured, and controlled
B.
Determine policies, objectives, and responsibilities to satisfy stakeholder needs
C.
Develop an approximation of the monetary resources needed to complete project activities
D.
Monitor cost performance to isolate and understand variances from the approved cost baseline
Monitor cost performance to isolate and understand variances from the approved cost baseline
What is the risk rating if the probability of occurrence is 0.30 and the impact if it does occur is
moderate (0.20)?
A.
0.03
B.
0.06
C.
0.10
D.
0.50
0.06
A complete set of concepts, terms, and activities that make up an area of specialization is known
as:
A.
a Knowledge Area
B.
a Process Group
C.
program management
D.
portfolio management
a Knowledge Area
The risk response strategy in which the project team acts to reduce the probability of occurrence
or impact of a risk is known as:
A.
exploit
B.
avoid
C.
mitigate
D.
share
mitigate
Which process is conducted from project inception through completion and is ultimately the
responsibility of the project manager?
A.
Control Quality
B.
Monitor and Control Project Work
C.
Control Scope
D.
Perform Integrated Change Control
Perform Integrated Change Control
Project management processes ensure the:
A.
alignment with organizational strategy
B.
efficient means to achieve the project objectives
C.
performance of the project team
D.
effective flow of the project throughout its life cycle
effective flow of the project throughout its life cycle
An element of the modern quality management approach used to achieve compatibility with the
International Organization for Standardization (ISO) is known as:
A.
Forecasting,
B.
Brainstorming.
C.
Historical databases.
D.
Cost of quality.
Cost of quality.
Which items are components of a project management plan?
A.
Change management plan, process improvement plan, and scope management plan
B.
Agreements, procurement management plan, and work performance information
C.
Schedule management plan, project schedule, and resource calendars
D.
Scope baseline, project statement of work, and requirements traceability matrix
Change management plan, process improvement plan, and scope management plan
Which project document is updated in the Control Stakeholder Engagement process?
A.
Project reports
B.
Issue log
C.
Lessons learned documentation
D.
Work performance information
Issue log