Topic 2, Volume B
Stakeholders can be identified in later stages of the project because the Identify Stakeholders
process should be:
A.
Continuous
B.
Discrete
C.
Regulated
D.
Arbitrary
Continuous
A graphic display of project team members and their reporting relationships is known as a:
A.
Resource calendar.
B.
Project organization chart.
C.
Resource breakdown structure (RBS).
D.
Responsibility assignment matrix (RAM).
Project organization chart.
Which item is a cost of conformance?
A.
Training
B.
Liabilities
C.
Lost business
D.
Scrap
Training
Which key interpersonal skill of a project manager is defined as the strategy of sharing power and
relying on interpersonal skills to convince others to cooperate toward common goals?
A.
Collaboration
B.
Negotiation
C.
Decision making
D.
Influencing
Influencing
Activity cost estimates and the project schedule are inputs to which Project Cost Management
process?
A.
Estimate Costs
B.
Control Costs
C.
Plan Cost Management
D.
Determine Budget
Determine Budget
In project management, a temporary project can be:
A.
Completed without planning
B.
A routine business process
C.
Long in duration
D.
Ongoing to produce goods
Long in duration
Which document in the project management plan can be updated in the Plan Procurement
Management process?
A.
Budget estimates
B.
Risk matrix
C.
Requirements documentation
D.
Procurement documents
Requirements documentation
Which type of probability distribution is used to represent uncertain events such as the outcome of
a test or a possible scenario in a decision tree?
A.
Uniform
B.
Continuous
C.
Discrete
D.
Linear
Discrete
Which change request is an intentional activity that realigns the performance of the project work
with the project management plan?
A.
Update
B.
Preventive action
C.
Defect repair
D.
Corrective action
Corrective action
Using parametric estimating, if an assigned resource is capable of producing 120 units per hour,
how many hours are required to produce 12,000 units?
A.
100
B.
120
C.
1,000
D.
1,200
100
Which stakeholder approves a project's result?
A.
Customer
B.
Sponsor
C.
Seller
D.
Functional manager
Customer
Which process involves determining, documenting, and managing stakeholders' needs and
requirements to meet project objectives?
A.
Collect Requirements
B.
Plan Scope Management
C.
Define Scope
D.
Define Activities
Collect Requirements