Topic 1, Volume A
Which tool or technique of the Define Activities process allows for work to exist at various levels of
detail depending on where it is in the project life cycle?
A.
Historical relationships
B.
Dependency determination
C.
Bottom-up estimating
D.
Rolling wave planning
Rolling wave planning
An output of the Create WBS process is:
A.
Scope baseline.
B.
Change requests.
C.
Accepted deliverables.
D.
Variance analysis.
Scope baseline.
A tool or technique used in the Control Procurements process is:
A.
Expert judgment.
B.
Performance reporting.
C.
Bidder conferences.
D.
Reserve analysis.
Performance reporting.
Configuration identification, configuration status accounting, and configuration verification and
audit are all activities in which process?
A.
Perform Quality Assurance
B.
Direct and Manage Project Work
C.
Monitor and Control Project Work
D.
Perform Integrated Change Control
Perform Integrated Change Control
Which tool or technique is used in the Estimate Costs process?
A.
Acquisition
B.
Earned value management
C.
Vendor bid analysis
D.
Forecasting
Vendor bid analysis
Which type of project management office (PMO) supplies templates, best practices, and training to
project teams?
A.
Supportive
B.
Directive
C.
Controlling
D.
Instructive
Supportive
Which Define Activities output extends the description of the activity by identifying the multiple
components associated with each activity?
A.
Project document updates
B.
Activity list
C.
Activity attributes
D.
Project calendars
Activity attributes
An input to the Identify Stakeholders process is:
A.
The project management plan.
B.
The stakeholder register.
C.
Procurement documents.
D.
Stakeholder analysis.
Procurement documents.
Identify Risks is part of which Process Group?
A.
Planning
B.
Executing
C.
Closing
D.
Initiating
Planning
Which conflict resolution technique searches for solutions that bring some degree of satisfaction to
all parties in order to temporarily or partially resolve the conflict?
A.
Force/direct
B.
Withdraw/avoid
C.
Compromise/reconcile
D.
Collaborate/problem solve
Compromise/reconcile
Which tool or technique is used in the Perform Integrated Change Control process?
A.
Decomposition
B.
Modeling techniques
C.
Resource optimization
D.
Meetings
Meetings
A logical relationship in which a successor activity cannot start until a predecessor activity has
finished is known as:
A.
Start-to-start (SS).
B.
Start-to-finish (SF).
C.
Finish-to-start (FS).
D.
Finish-to-finish (FF).
Finish-to-start (FS).
Page 12 out of 66 Pages |
Previous |